C&P is one of the very few accredited inspection bodies that can provide you with DOSH (Department of Occupational Safety and Health) certification services for the import of pressure vessels and steam generators under the occupational safety and health act 1994 occupational safety and health (plant requiring certificate of fitness) regulations 2024. According to the amendment to the First Schedule of the aforementioned regulation, C&P, since March 23rd, 2017 has been included with no. 10 as Authorized Inspecting Body approved by DOSH for the inspection and certification of pressure equipment intended for the Malaysian market. C&P, through its partner C&P Inspection Sdn Bhd, and its qualified and C&P controlled inspectors, is able to give you the necessary support even locally.
Read more ...
Occupational safety and health act 1994 occupational safety and health (plant requiring certificate of fitness) regulations 2024, is a regulation issued by the Department of Occupational Safety and Health which defines the requirements on the basis which the Chief Inspector authorizes the construction or import of unfired pressure vessels (Unfired pressure vessels, Steam boilers). Part III sets out the requirements that the importer must comply with in order to be authorized to install such equipment in the Malaysian Federation.
Specifically:
- (i) must not have been previously used or deteriorated from any cause;
- (ii) all materials used in construction must, regarding to chemical composition, quality, production process, number and nature of tests, inspections and indications of the certified manufacturer, comply with the provisions of one of the codes, standards or specifications set out in the Fourth Schedule to this Regulation;
- (iii) regarding design, construction methods and testing, the manufacturer shall comply with the requirements of any of the codes, regulations or specifications set forth in the Fourth Schedule of the DOSH Regulations.
- (iv) during the construction period it must have been under the supervision of an authorized member of the control bodies (Authorized Inspecting Body) which of in the fourth schedule (First schedule where line 10 included C&P) to this Regulation;
- (v) must be equipped with accessories that comply with the provisions of the DOSH Regulations.
Authorized Inspecting Body Authority (CP) issues the manufacturer with a certificate, particulars of test and examination report “Ninth schedule”, certifying that the requirements of the DOSH Regulations have been met and that must subsequently be accepted by the Chief Inspector (Malaysian state authority) as evidence of compliance with the above requirements.
How to...
To apply for certification, is required to submit:
- a request for quotation/intervention form AM042N, specifying that the inspection is required in accordance with DOSH regulations;
- construction drawings;
- design calculations;
- the welding book consisting of welding procedures, welding process qualifications and welder qualifications;
- the inspection plan.